Sikorsky CH-53K programme puts gearbox issues behind it

Download: Printable PDF Date: 13 Apr 2016 04:05 (UTC) category:
Publisher:
Sikorsky CH-53K programme puts gearbox issues behind it - Manufacturer publisher
Tatjana Obrazcova
Country: United States Aircraft: Helicopters
Source: Flightglobal

US Naval Air Systems Command (NAVAIR) appears to be confident that the Sikorsky CH-53K programme has put the gearbox failures and parts delays experienced prior to first flight in October 2015 behind it, but the Lockheed Martin-owned helicopter manufacturer won’t receive bonus cheques for lateness.

The US Government Accountability Office (GAO) recently stated that the King Stallion’s planned entry into low-rate production has been delayed eight months to February 2017 because of technical difficulties.

The aircraft is being developed for the US Marine Corps to replace the heavy-lift CH-53E, and should be ready for duty in 2019.

Although the US government bears the ultimate cost of delays and overruns, NAVAIR says schedule incentives were part of the arrangement “and Sikorsky was impacted due to schedule slides”.

The latest development cost estimate stands at $6.8 billion, $2 billion more than originally imagined.

Asset Image

Sikorsky/Lockheed Martin

The super-heavy-lift helicopter’s two critical technologies are the split torque gearbox and seven anhedral swept-tip composite main rotor blades and both are now flying on the first two engineering design model (EDM) aircraft. However, problems reported with the main gear box did set back the overall test schedule by delaying first flight.

“The redesigned components are flying in the test aircraft and are performing well,” confirms NAVAIR in an email to Flightglobal. “The redesigned components are flying in both test assets currently flying, and no further changes are anticipated. There has been no impact to the flight schedule because the changes were made prior to first flight.”

The programme has also been working with unnamed suppliers to “find efficiencies” and all redesigned components were ground testing prior to retrofit and flight on EDM-1. NAVAIR expects the third and fourth aircraft to join the test campaign “before the end of summer 2016”.





Recommended

TAROM took delivery of its first Boeing 737 MAX

Boeing, TAROM and CDB Aviation have celebrated the delivery of the airline’s first 737‑8, marking the arrival of Romania’s first Boeing 737 MAX and a key milestone in the national carrier&...

Embraer adds BermudAir as its second E‑Freighter operator

Embraer and Regional One announced that BermudAir has become the world’s second operator of the Embraer E‑Freighter, marking the aircraft’s debut in the Americas with the airline&rsqu...

Drukair, Royal Bhutan Airlines selects CFM LEAP-1A engines to power 5 Airbus A320neo family aircraft

Drukair – Royal Bhutan Airlines, the national flag carrier of the Kingdom of Bhutan, has announced its decision to equip five Airbus A320neo‑family aircraft with CFM International LEAP‑1A engine...

Airbus is expanding its delivery capacity for the A320 family in Toulouse with a new integrated center

Airbus has officially unveiled a new delivery center at its Jean‑Luc Lagardère site, northwest of Toulouse, marking a significant milestone in the industrial ramp‑up of the A320 Family. Purpose...

Android Apps development in Riga, Latvia